Gitlitz Garage: August 2007



August 1, 2007 -- The walls of the garage now have blocking for the wainscot. It will be installed in a day or so.


August 2, 2007 -- Fiberglass insulation is being installed in the walls. Sound insulation will be installed around the bath room upstairs. This will complete the insulation.


August 3, 2007 -- The closet has been built over the bottom staircase.


August 3, 2007 -- Wainscot has been installed along the bottom of the walls on the upstairs room.


August 3, 2007 -- The closet is near the stairwell. It is over the lowest set of stairs.


August 6, 2007 -- Wainscot of concrete board is being installed in the garage. Narrower pieces of concrete board will be installed on top of this one to make it look like T-111.


August 6, 2007 -- The stairs go down under the newly added closet.


August 8, 2007 -- The sheet rock has been delivered. It will be installed in the next day or two.


August 9, 2007 -- The second layer of cement board is now installed. The vertical boards make it look very much like T-111 suitable for garages (non flammable).


August 10, 2007 -- The concrete board "T-111" in the garage is finished. It will also be installed in the downstairs storage room.


August 14, 2007 -- Sheet rock is being hung in the garage. It should be finished tomorrow and painting will begin.


August 14, 2007 -- The garage needs the deck finished and then the outside will be complete. A brick walk will be built between the house and garage.


August 17, 2007 -- Sheet rock has been hung in the garage. It will be finished starting Monday.


August 17, 2007 -- 5/8" thich sheet rock was hung downstairs in the garage. The wires in the ceiling are for the garage door opener.


August 31, 2007 -- The sheetrock is finished and ready for priming. The double door frame leaning next to the closet gets installed in the closet.