October 5, 2007 -- The overhead garage door has been installed. It has not been painted yet. The column supporting the upstairs deck is also in place.


October 5, 2007 -- The deck has been installed over the storage room. Soon the railings will be built.


October 12, 2007 -- There will be a stoop outside these doors and a side walk leading to the cottage.


October 16, 2007 -- The garage has a brick stoop leading to a brick sidewalk to the house. The door thresholds will have brick supports under them today.


October 18, 2007 -- The deck railing is complete except for painting. The white at the bottom is the deck waterproofing from the deck.


October 22, 2007 -- The railing makes a nice deck over the storage room. It will be painted green to match the house trim.


October 22, 2007 -- The bathroom floor has been tiled. It matches the tile in the house bathrooms. In the next day or so, the walls will be tiled.


October 22, 2007 -- The windows have plantation shutters mounted over the lower sash. The shutters open and close and even open like doors. Notice the hinges.


October 22, 2007 -- The walk connects the house and cottage. Notice the very nice brickwork at the corners.


October 31, 2007 -- The upstairs is getting finished. Carpet is down. Door hardware is installed. The closet shelf and rod will be installed today.