Residential Contractors

(843) 846 - 2500

Keller Residence: January 2007



January 9, 2007 -- The driveway is covered with wood chips. Much of the protecive fencing is in place.


January 17, 2007 -- Footers for the house and garage have been dug.


January 24, 2007 -- Steel is placed in the footers. They were ready for inspection on January 22, but rain filled the trenches. They are now clean, inspected and ready to pour.


January 24, 2007 -- A view of the footers looking South. The large footer is for one of the chimneys.


January 24, 2007 -- Pouring is underway. Concrete was pumped because the ground was soft.


January 25, 2007 -- Footers are poured. Block laying will begin in a day or so.


January 25, 2007 -- The power pole for temporary power is installed.


January 25, 2007 -- The job site sign is up and lettered.


January 29, 2007 -- The footer is finished and most of the blocks are in place.


January 29, 2007 -- The house blocks are up. A steel beam will run down the center of the house.