Keller Residence: January 2008
Click on the photos to see an enlargement.
January 10, 2008 -- The ipe (pronounced e-pay) decks have been finished. They look very nice. The glare from the sun washes out the color a bit in this photo.
January 10, 2008 -- The kitchen now has beams on the ceiling. They will be finished with crackle paint to simulate the look of old beams. There is also a beam on the close wall that is out of the camera range.
January 10, 2008 -- The scaffold is gone from the Brays room. In the next few days, the mantle will be started. The A/V cabinet on the right has yellow masking tape around it.
January 23, 2008 -- A built-in in the mud room has a dog bed in the bottom, two drawers and boot storage bins in the top.
January 23, 2008 -- The porches have railings and framing to hold screen. They will be painted soon.
January 30, 2008 -- The garage apartment has the floors finished. Blue masking tape is still on the baseboards. Paper is down to protect the floors.
- Click Here to return to the Past Projects Page
- [Home]
- [News]
- [Past Projects]
- [Campbell]
- [Causey]
- [Elloree]
- [Gitlitz Cottage]
- [Gitlitz Garage]
- [Griffin]
- [Groman]
- [Historic]
- [Hoats]
- [Keller]
- [Dec 06]
- [Jan 07]
- [Feb 07]
- [Mar 07]
- [Apr 07]
- [May 07]
- [Jun 07]
- [Jul 07]
- [Aug 07]
- [Sep 07]
- [Oct 07]
- [Nov 07]
- [Dec 07]
- [Jan 08]
- [Feb 08]
- [Mar 08]
- [Apr 08]
- [May 08]
- [Kumar]
- [Langford]
- [Lord]
- [Lowcountry Plantation]
- [McCormack]
- [McNeil]
- [Ponds]
- [Rizer]
- [Schuld]
- [Weiss]
- [Select A Builder]
- [Services]
- [FAQ]
- [Contact Us]
- [About Us]
- [Testimonials]
Copyright, 2009, Ponds & Sons Construction Company, Inc. dba Ponds & Sons