Residential Contractors

(843) 846 - 2500

Schuld Residence: December 2006



December 4, 2006 -- The front of the house with most of the windows installed.


December 4, 2006 -- The chimney flue and flue liner are installed.


December 5, 2006 -- A beautiful elliptical window.


December 5, 2006 -- Arched windows overlooking the driveway.


December 6, 2006 -- Windows are installed. The ground is still wet.


December 6, 2006 -- Doors going on to the rear porch are installed.


December 8, 2006 -- Electrical rough in well under way.


December 14, 2006 -- The side stoop has decking and steel and is ready for concrete.


December 14, 2006 -- Bricks have been delivered for the chimney.


December 14, 2006 -- Fill dirt is put in place for the spa deck.


December 15, 2006 -- The footer and steel are ready for concrete for north service yard.


December 15, 2006 -- The footer and steel are ready for concrete for south service yard also.


December 18, 2006 -- Framing to support the garden tub is completed in the master bathroom.


December 18, 2006 -- Rough in wiring is proceeding nicely.


December 20, 2006 -- Exterior trim has started.


December 21, 2006 -- Exterior trim really sets off the elliptical window. Compare this to the Dec. 4 photo which has no exterior trim.


December 21, 2006 -- The windows are beautiful with the exterior trim added. Compare this to the window without exterior trim on Dec. 5.


December 21, 2006 -- The pad for a spa has been filled and formed.