Residential Contractors

(843) 846 - 2500

Schuld Residence: November 2006



November 1, 2006 -- Another vaulted ceiling.


November 2, 2006 -- Look at the man in the white shirt near the front porch.


November 2, 2006 -- The rear porch is poured.


November 3, 2006 -- A dormer in the activity room.


November 8, 2006 -- House wrap starts.


November 8, 2006 -- More rain.


November 8, 2006 -- Water puddles everywhere.


November 9, 2006 -- The house is wrapped.


November 9, 2006 -- The back porch header is built in place for an exact fit.


November 9, 2006 -- The front porch header is also built in place for a perfect fit.


November 9, 2006 -- The front porch header is lifted into place.


November 10, 2006 -- Front porch rafters are added.


November 10, 2006 -- Plumbing rough in is nearly finished.


November 10, 2006 -- The gable over the front door is built.


November 13, 2006 -- Steel supplements the wooden rafters in strategic locations.


November 14, 2006 -- The front porch roof is sheathed.


November 14, 2006 -- Side view of front porch.


November 15, 2006 -- The chimney is ready to assemble.


November 15, 2006 -- The flue and flue liner.


November 15, 2006 -- The back porch header is in place.


November 16, 2006 -- More rain...


November 16, 2006 -- ...and puddles.


November 17, 2006 -- The back porch with header and roof in place.


November 17, 2006 -- A beautiful herringbone layout of firebrick is started.


November 17, 2006 -- A rear view of the house with the back porch in place.


November 21, 2006 -- Our windshield. It is not supposed to sleet in South Carolina Low Country.


November 21, 2006 -- The framers built an ice man.


November 27, 2006 -- The house with front porch roof in place.


November 28, 2006 -- Water heaters have been installed.


November 28, 2006 -- Bath tubs have been installed for a while.


November 28, 2006 -- Heating and air conditioning has been roughed in.


November 30, 2006 -- Windows are being installed.