Schuld Residence: September 2006
September 5, 2006 -- The double car garage area is filled and packed.
September 5, 2006 -- Center piers are completed and ground is leveled in preparation for pouring crawl space slab.
September 11, 2006 -- Trusses for the first floor arrive.
September 11, 2006 -- The crawl space slab is poured.
September 14, 2006 -- Rains have come.
September 20, 2006 -- Trusses are being placed. The open area on the front is the front porch.
September 22, 2006 -- Trusses are in place and ready for subflooring.
September 25, 2006 -- The first floor subflooring is finished.
- Click Here to return to the Past Projects Page
- [Home]
- [News]
- [Past Projects]
- [Campbell]
- [Causey]
- [Elloree]
- [Gitlitz Cottage]
- [Gitlitz Garage]
- [Griffin]
- [Groman]
- [Historic]
- [Hoats]
- [Keller]
- [Kumar]
- [Langford]
- [Lord]
- [Lowcountry Plantation]
- [McCormack]
- [McNeil]
- [Ponds]
- [Rizer]
- [Schuld]
- [Aug 06]
- [Sep 06]
- [Oct 06]
- [Nov 06]
- [Dec 06]
- [Jan 07]
- [Feb 07]
- [Mar 07]
- [Apr 07]
- [May 07]
- [Jun 07]
- [Jul 07]
- [Aug 07]
- [Sep 07]
- [Oct 07]
- [Nov 07]
- [Dec 07]
- [Jan 08]
- [Weiss]
- [Select A Builder]
- [Services]
- [FAQ]
- [Contact Us]
- [About Us]
- [Testimonials]
Copyright, 2009, Ponds & Sons Construction Company, Inc. dba Ponds & Sons