Weiss Residence: July 2008
Click on the photos to see an enlargement.
July 1, 2008 -- The garage apron will be poured tomorrow if all goes well. The surface will be oyster shell with a brick border.
July 3, 2008 -- The garage parking apron is being poured. It will have an oyster shell finish. The white particles on the finish are crushed oyster shells.
July 8, 2008 -- At the foot of the rear (drive side) steps, the oyster shell concrete has a brick border that was laid today.
July 8, 2008 -- The air conditioner condensing units now have a concrete pad. The raised pad to the right is for a future generator. A fence will be built in a few days to hide this equipment.
July 8, 2008 -- The parking apron is finished and a brick border is being laid. It will match the one at the rear steps.
July 10, 2008 -- A service yard fence is being built to screen the air conditioning condensing units and the future generator. A similar one (but shorter) will be built off the garage to screen the propane tank.
July 11, 2008 -- The parking apron is finished. It is made of oyster shell concrete with a brick border. Note the service yard fence at the end of the garage. It screens the propane tank.
July 11, 2008 -- Brick are being cut for the column caps. They will be laid today, weather permitting.
- Click Here to return to the Past Projects Page
- [Home]
- [News]
- [Past Projects]
- [Campbell]
- [Causey]
- [Elloree]
- [Gitlitz Cottage]
- [Griffin]
- [Groman]
- [Historic]
- [Hoats]
- [Keller]
- [Kumar]
- [Langford]
- [Lord]
- [Lowcountry Plantation]
- [McCormack]
- [McNeil]
- [Ponds]
- [Rizer]
- [Schuld]
- [Weiss]
- [Jul 07]
- [Aug 07]
- [Sep 07]
- [Oct 07]
- [Nov 07]
- [Dec 07]
- [Jan 08]
- [Feb 08]
- [Mar 08]
- [Apr 08]
- [May 08]
- [Jun 08]
- [Jul 08]
- [Select A Builder]
- [Services]
- [FAQ]
- [Contact Us]
- [About Us]
- [Testimonials]
Copyright, 2009, Ponds & Sons Construction Company, Inc. dba Ponds & Sons