Lowcountry Plantation Remodel: October 2007
Click on the photos to see an enlargement.
October 11, 2007 -- The last cabinets finally came in and were installed. The undercounter light still needs to go under the new cabinet (left on the top). You can see the wire for the light.
October 12, 2007 -- The window from the stairway to the dining room has been removed. Sheet rock is on the dining room side. The stairwell will be finished today.
October 12, 2007 -- The access to under the house now has a cover. It can be easily removed for access.
October 16, 2007 -- The bath hardware (mirror, toilet paper holder and towel ring) have been installed.
October 16, 2007 -- The cypress paneling in the stairway has been replaced where the window was removed. It will be stained to match the existing cypress.
October 16, 2007 -- Floodlights are now installed at two corners of the house. They are on a dimmer. This corner is the kitchen. The other corner (not shown) is the master bedroom.
October 18, 2007 -- The walls have been painted with their final coat. The ceiling is really a green color even though it is not obvious in the photo. Painting should be complete today.
October 22, 2007 -- The stairway wall boards that are where the window was have been stained and match nicely.
- Click Here to return to the Past Projects Page
- [Home]
- [News]
- [Past Projects]
- [Campbell]
- [Causey]
- [Elloree]
- [Gitlitz Cottage]
- [Gitlitz Garage]
- [Griffin]
- [Groman]
- [Historic]
- [Hoats]
- [Keller]
- [Kumar]
- [Langford]
- [Lord]
- [Lowcountry Plantation]
- [May 07]
- [Jun 07]
- [Jul 07]
- [Aug 07]
- [Sep 07]
- [Oct 07]
- [McCormack]
- [McNeil]
- [Ponds]
- [Rizer]
- [Schuld]
- [Weiss]
- [Select A Builder]
- [Services]
- [FAQ]
- [Contact Us]
- [About Us]
- [Testimonials]
Copyright, 2009, Ponds & Sons Construction Company, Inc. dba Ponds & Sons